Official ISTQB Definition

Documentation describing the test objectives to be achieved and the means and the schedule for achieving them, organized to coordinate testing activities.

In simple words

The document that answers ‘what, when, how, and by whom’ for the testing effort — scope, schedule, risks, entry and exit criteria.

Exam tip

In CTFL v4.0, planning is iterative and the test plan is updated as risks and progress change.